Back to intro or goto next section or goto dam update page

The steel dam at Redridge,upstream side The timber dam at Redridge

The Dams of Redridge

A stamp mill requires water for use in the "wash" of it's operations to separate the copper mineral from the rock it was mined from. One of the reasons the Atlantic mill was placed in Redridge was the fact that it had a stream, the Salmon Trout River, that could be dammed up and used to supply water for their mill. The first dam constructed on this site was a timber crib dam built of timber, loose rock and earth. The main portion is 53 feet thick at the bottom, 28 feet thick at the top and 50 feet high. The length across the stream is 51 feet at the bottom, 228 feet at the top. The timbers were 14 inches thick and hewed flat, bound together with inch square drift bolts. The upstream face was lined with four inch plank, which was then covered in 2 inch plank. An earthen embankment was constructed on the inner side of the dam with a slope of 1.5 to 1. When referring to the earthworks of this dam, the word constructed is somewhat of a misnomer. All of the work on this dam was done by hand, no heavy construction equipment was available, so all of the dirt was literally shoveled into place. At the base of the dam, near the east bank of the river, there were two cast iron pipes 24 inches in diameter with gate valves placed about 170 feet back from the toe of the dam. These gates were then closed to allow the dam to fill. The water was transported from dam to mill via a launder 18"X36" in cross section, 2050 feet long and dropped 5 inches per 100 feet of length.(25) The cost to Atlantic Mining Company for the dam was a total of $24,161.58. Below is a picture of this dam as it looked in 1951 after the steel dam had been drained.
The timber dam at Redridge in 1951

The current picture of this dam may be seen at the top of this section. An intriguing feature of this timber dam is the offshoot of the dam just to the west of the main portion. It can be seen in the 1951 photo on the right side of the dam. It took a long time for this researcher to come up with a reason why it is there in the first place. The area behind this part of the dam does not look like it would have held back water very often. There is a large depression several feet behind it, but it is not currently connected to the rest of the old reservoir that the old dam still holds. The diagram of the Atlantic site from the 1895 Atlantic stockholder report shows water behind this portion, though it is possible that this area was filled in somehow during construction of the new dam or by deposits while it was submerged behind the new dam. The answer comes when one looks at the 1951 picture, and then at the Redridge site plan. The small channel that this downstream of this portion is angled in such a way to suggest that it is where the small creek coming from the west emptied into the Salmon Trout River.

Reports from the Atlantic Mining Company in 1900 stated that the crib dam was showing signs of weakening(26) and since Baltic Mining Company was in the process of building it's own stamp mill at the site, a new larger dam was to be constructed so both mills would have enough water to operate. Horace Stevens in the Copper Handbook of 1900 "The peculiar conditions prevailing at the mouth of the Salmon Trout rendered a dam of ordinary pattern almost out of the question."(27) They were peculiar in that there were no nearby sources of stone for a masonry dam, and the site was far too remote to haul in the materials necessary to build a regular dam. Also, copper prices had boomed in the years since Atlantic Mine first built their mill, so the companies could not wait for a conventional dam, especially with such short construction seasons that are typical to the area. Atlantic and Baltic mills needed something fast, and so they decided to try a new technology, steel dams.

Redridge steel dam under construction

The photo above shows the dam in early phases of construction.(28) The steel portion of this dam is 464 feet long(29) and at it's central portion is 74 feet tall. The steel portion of the dam is flanked by concrete core earthen embankments on each end to stretch the total length of the dam to 1006 feet. Water was taken from the dam through three valves near the ends of the steel structure 20 feet below the crest. Sources of information on this feature of the dam vary somewhat as to what dimensions these were. Company reports do not mention it, Copper Handbook lists 38 inch diameter pipes, Engineering News listed 24" valves(30). Personal Valve outlet for Atlantic feed examination of the remains of the Atlantic feed (photo at right) shows that this particular pipe is 24" in diameter. The size of the pipe leading down to the Baltic is also contradicted by the Sanborn maps of that facility, which list one 36" diameter pipe leading into the mill instead of a 38" pipe reported in the other sources. In the original writing of this report, I was unable to measure the baltic pipes because they were buried in snow. But on a trip back there in October 1997 I was able to take the photo below. What I found was a diameter changing fitting with a cleanout in the middle. The left side of the fitting measured 24", and the right side measured 38" (both outside diameters)(31)

pipe fitting coming from Baltic feed

The steel dam, remarkable as it is, has features that separated it from the other dams of it's type. For one, the dam was designed with a substantial concrete base and a large angle from horizontal, depending on it's own weight and the weight of the water to hold it in place. Also, unlike the other steel dams built, this one was not built as a weir, or overflow dam, but instead used a spillway to deal with excess.

Here is a series of photos of this spillway.

weir1.jpg - The spillway nearing completion

weir2.jpg - The spillway during spring flooding in 1942. The trestles shown starting from foreground are 1. to steel dam, 2. to Baltic Stamp mill (only one still in existance), 3. overpass for roadway to Freda, 4. railroad trestle to mill along shore.

weir3.jpg - The gates to the spillway during a spring flood. As you can see, water has already destroyed two of the wood sections.

gates1.jpg - The gate supports as they look present day. The panels between them were removed in 1966.

NEW! bridgepilinginweir.jpg - Shot in early May 2002, this concrete pier is one of the supports for the trestles that crossed over the weir.


This spillway was 400 to 600 feet long (depending on which source you look at), 30 feet wide, 4 feet deep, and 6 feet below the top level of the dam. This spillway was wrecked in the spring of 1905 and had to be completely rebuilt. A major question this author had when researching the dam is why was the spillway built in the first place? The other two steel dams built in that period were both overflow dams with no spillway. Unfortunately no real information on this could be found, as the records from the firm that designed the dam had either been lost or destroyed.(32) One guess would be that since the town was directly downstream, the sound of water crashing down from 74 feet up would not be welcome for any prolonged period. William Brinkman, in an article in the Daily Mining Gazette, reported that when the dam overflowed in the spring of 1941 the roar could be heard from his home in the village.(33) This may not be the case though, as photos of the Hauser Dam in Montana (an overflow steel dam) show what appear to be dwellings on one bank of the river.(34) Another guess might be that although the engineers designed it strong enough to survive overtopping, they did not want to risk it with such a new dam technology. The risk would be that since this dam had a larger angle than the other steel dams, the water would be falling much closer to the foundations, risking serious undermining. The overtopping incident in 1941 came close to wiping out the road below the dam and convinced the owners of the dam in 1943 to open the discharge valves at the foot of the dam as much as possible. Other attempts were made in the 50's to open them further, but the valves had been too rusted and jammed with debris. Even with the discharge valves open, the dam again approached flood stage in the spring of 1976, this time it did not overflow, but the trestles over the spillway were in serious danger of collapse, which would have torn the road apart when the debris hit it. By 1979 the Copper Range Company, owners of the dam, feared that the disrepair of the spillway would lead to a dam collapse. To eliminate the possibility of that happening, the company cut 4 4' X 8' openings in the steel work just above the concrete base. These holes can be seen in the photo at the beginning of this section.

Despite having little care since the mills it supplied water to closed down, the dam itself is in rather good condition, but cutting the holes in the dam exposed the concrete below to extremely harsh conditions concrete damage on steel dam (water rapidly rushes over this area during spring thaw) and much of the facing concrete there has crumbled away (photo at right). The dam has not had a use in over 70 years, and yet it still stands as a testament to engineering know how in the early part of this century. In 1985 a plaque was placed at the site listing it as a civil engineering landmark by the Michigan section of the American Society of Civil Engineers (photo below).

UPDATE: In May of 2002 I made another trip to Redridge to take photos. I felt I had to after reading on copperrange.org that the timber dam is in serious danger of being lost to us. To access the photos and commentary please click here.

commemorative plaque at Redridge



This page hosted by   Get your own Free Home Page